The story so far..

We will be posting pictures and updates quarterly on progress so you can follow the Quail Ridge story and join us on this amazing journey.

Click on the sections below to read more about the updates.

Spring 2017

Quail Ridge Country Club Newsletter – Spring 2017   Hi all, just a quick update on what we’ve been up to in the last few months. We now have 23 occupied homes in the Country Club, with a further 31 sold. We currently have 13 houses under construction. We have 36 sites with specified plans […]

Autumn 2017

Quail Ridge Country Club Newsletter – Autumn 2017 Our first Duplex (Artisan/Parisian) is under construction and is due to be completed on the 8th of September 17 “the Artisan” has been sold and we have strong interest in the “Parisian” at the special price of $571,000. Our next Duplex will be built in January 18. […]

Spring 2015 – Summer 2016

Time has certainly flown past as we have been very busy and happy with the progress as you can see from the marketing/development plan. Enquiries continue at a high level with our building schedule booked up until July 2017. We do however have one town house available in February please call for an appointment to […]

Spring 2015

It is with great pleasure that we welcome our first two residents who moved into Quail Ridge in September. These two homes, a Stonebrook and Grove design, are a major milestone for Quail Ridge Country Club.     We are very proud of the quality achieved in the building and finish of these two houses; […]

Winter 2015

Thanks to the mild winter here in the “winterless North”, construction on the first two homes and the show home has made steady progress. The first home is scheduled for completion mid-September, the second in October and the Show Home in January 2016. We are excited to see all the activity and progress taking place […]

Autumn 2015 update

Somehow summer came and went in the blink of an eye, we are going full steam ahead with the build of 3 houses and the infrastructure, as you can see from the pictures below. So now for the best news of the year – The first 3 building consents have all been approved and issued […]

Summer 2014-15 update

So Christmas has come and gone and the start of a new year is upon us, on behalf of all of the team at The Quail Ridge Country Club we hope you have fantastic and happy 2015. So now for the best news of the year – The first 3 building consents have all been […]

Spring 2014

We are now well under way with this exciting new development, to date we are pleased to say that 32% of residential homes of stages 1 and 2 have been acquired and it is because of this incredible rate the we have now started to engage the new team to assist David Penberthy, who is still […]

Winter 2014 update

Over the last two months much has been happening in Stage 1. 1. Working with Top Energy for our power supply. They are currently working in Rainbow Falls Road so that the power lines will go underground. 2. Entrance way has been constructed and services installed. 3. Roading has been formed and metalled. 4. Storm […]

Spring 2013 update

We issued our tender documents for the roading and infrastructure in October to selected contractors. We are delighted to announce that we have awarded the contract to JSB Construction Limited of Kerikeri for the first three stages, work commenced on the 11th of November 2013. Your hosts, Don, Jill, David, Elena